Projects
What we have done so far. Lots of exciting project coming up.
  • T228 - TBM Assembly

    Project T228, assembly of Hitachi Zosen EPB TBM on sloped tunnel flooring.

    Deployment of:-

    – Skid Sliding System for the horizontal maneuvering of TBM on tunnel floor.

    – Smart Gripping Hydraulic Jack for pulling of TBM on cradle.

    – Synchronous Hydraulic Jack operation on vertical lifting/lowering of TBM.

    Pioneering the use of Hydra-Slide’s innovative sliding method featured in major industrial news online! (Click image to learn more)

    Yu Sin Engineering Uses a Hydra-Slide HT300 to Move Boring Machine for Singapore Tunnel Project

     

    See the operation in action! (Original Link)

     

    Giving back to the society during our low-key periods. (Click image for more info)

    23 men volunteer to cook for a cause

    List of completed and on-going projects.

    Project Duration Project Title Project Value
    AUG 2014 NS3 MARYMOUNT $200,000 – $500,000
    SEP 2014 – NOV 2014 DOWNTOWN LINE 3 C929A $200,000 – $500,000
    OCT 2014 – NOV 2014 HOLLAND SHAFT > $200,000
    NOV 2014 – JAN 2015 PIE TBM 2 MAIN DRIVE $100,000 – $300,000
    NOV 2014 – JAN 2015 PIE TBM 3 ASSEMBLY $200,000 – $500,000
    DEC 2014 – FEB 2015 SHIPYARD ASSEMBLY $200,000 – $500,000
    JAN 2015 – MAR 2015 HONGKONG DISMANTLE $400,000 – $700,000
    FEB 2015 – APR 2015 EW3 PAYA LEBAR $200,000 – $500,000
    MAR 2015 – MAY 2015 EW3 KALLANG $200,000 – $500,000
    APR 2015 PIE MAIN DRIVE $100,000 – $300,000
    JUN 2015 – AUG 2015 BENOI JURONG ISLAND $200,000 – $500,000
    JUL 2015 – SEP 2015 T202 THOMSON TBM ONE $200,000 – $500,000
    SEP 2015 – JAN 2016 T202 THOMSON TBM TWO $200,000 – $500,000
    OCT 2015 – NOV 2015 EW3 DISMANTLING $100,000 – $400,000
    NOV 2015 – JAN 2016 T207 TBM 1 & 2 ASSEMBLY $200,000 – $500,000
    NOV 2015 – FEB 2016 JIPCT DISASSEMBLY $200,000 – $500,000
    JAN 2016 – MAY 2016 T207 TBM 3 & 4 ASSEMBLY $200,000 – $500,000
    FEB 2016 – APR 2016 JIPCT REASSEMBLY $200,000 – $500,000
    FEB 2016 – APR 2016 EW1 DISMANTLING SLURRY $200,000 – $500,000
    FEB 2016 – APR 2016 EW1 DISASSEMBLY EPB $200,000 – $500,000
    APR 2016 – AUG 2016 T226 ASSEMBLY > $200,000
    MAY 2016 – OCT 2016 T211 ASSEMBLY TBM (4x)
    $300,000 – $600,000
    MAR 2017 – APR 2017 T226 DISASSEMBLY SQUARE     TBM
    > $200,000
    DEC 2016 – FEB 2017 T220 ASSEMBLY EPB & SLURRY
    $200,000 – $500,000
    MAR 2017 – MAY 2017 JIPCT DISMANTLING
    $200,000 – $500,000
    MAY 2017 – JUN 2017 T228 TBM U-TURN
    $200,000 – $500,000
    FEB 2017 – SEP 2017 T207 EPB DISMANTLING
    $600,000 – $800,000
    AUG 2017 – OCT 2017 T211 DISMANTLING SLURRY
    > $1,000,000
    JAN 2018 – MAR 2018 T228 TBM DISMANTLING & TUNNELING WORKS $300,000 – $600,000
    DEC 2017 – ON-GOING  T311 TBM ASM/DIS TBM & TUNNELING WORKS  > $1,000,000

     

    DUBAI METRO PROJECT (MHI TBM INSTALLATION WORKS)

    Tailing of Dia 9.50m MHI TBM Front body bottom unit

    Lowering of Dia 9.5m MHI TBM Front

    Installation of Cutter Motor

    Assembly of TBM Parts in Order
    DUBAI METRO PROJECT (MHI TBM DISASSEMBLY WORKS)

    Setting of Lifting Lugs

    Tailing of Cutting Head

    Lifting up of Rear Body

    Tailing of Middle Body
    Project C705 - Removal of TBM Bearing unit within Tunnel

    Adjustment of TBM Main Bearing

    Tilting of TBM Main Bearing
    Project C503 - Assembly of LOVAT TBM

    Lowering of TBM Main Bearing

    Lowering of TBM Middle Shield
    Project T-02 - Assembly of NKK TBM

    Assembly of TBM Cutter Motor

    Assembly of TBM Front and Middle Shield
    Project C-853 - Assembly of Kawasaki TBM

    Lowering of TBM Main Bearing

    Assembly of TBM Main Bearing to Middle Shield

    EW3 – Disassembly of Hitachi Zosen TBM (for reassembly)


    Fabrication of Support Structure for removal of EPB Screw

    Removed Front Body tandem lifted to be placed flat for escorting to reassembly site

    Removal and hoisting of Shield Jack towards surface

    Removal of Screw from TBM, tilted as screw's length is longer than Tunnel diameter

    EW3 – Reassembly of Hitachi Zosen TBM


    Pre-installation of Front Body Assembly components such as Shield Jack and Cutter Motor before lowing Front Body into Tunnel

    Front Body tandem lifted to be lowered into Tunnel

    Lowering of Middle Body into Tunnel, to be connected with Front Body

    Placement and adjustment of TBM Screw towards and within TBM Body

    T202 – Assembly of Kawasaki TBM


    Tandem Lifting Operation to Tilt TBM Body

    Lowering of TBM Cutter Head

    TBM Cutter Head lowered precisely onto TBM Front for assembly

    Installation of TBM Cutter Motor Units

    Installation of TBM Erector Unit onto Middle Body Assembly

    Fabrication of Pulling Bracket according to P.E.'s specification

    Installation of Pressure Hose for TBM operation

    Installation of Slurry Pipes for slurry removal process

    T207 – Assembly of Japan Tunnel Systems Corporation TBM


    TBM Front Body Section ready to be hoisted

    Front Body Section lowered to attach onto Front Body Assembly on Support Cradle

    Lowering Middle Body onto Support Cradle in Tunnel

    Sliding/Pulling of TBM along TBM Support Cradle

    Installation of Shield Jacks onto Middle Body in Tunnel

    Lowering and Installation of Cutter Head towards Front Body on Support Cradle

    EW1 – Disassembly of Hitachi Zosen TBM


    Lifting of Back Up Car using Chain Blocks to be loaded onto Flat Car for removal

    Cutting of Screw Conveyor

    Removal of Shield Jack units

    Removal of Cutter Motor totaling of 6 Units

    Removal of Man Lock

    Removal of Main Bearing

    Removal of Gripper

    Last Trimming Works on TBM body before handing over

    T226 – Assembly of Japan Tunnel Systems Corporation Square TBM


    Square TBM Body per-assembled below lowering into Tunnel

    TBM Body welded with customized Jacking Bracket for Maneuvering with Rollers

    Jacking up TBM for re-positioning of Rollers and Track for change in traverse direction

    Installation of TBM Shield Jacks and other TBM components

    NS3 Project – Cable Tunnel in PIE


    Manual Jacking of the TBM into Launching Chamber

    Lowering and Assembly of Erector

    Manual Jacking of TBM into Launching Chamber (Top View)

    Assembly of TBM Gantries

    NS3 – Marymount Assembly of Herrenknecht TBM


    Front Body's Assembly ready to be hoisted

    Connection of Front Body's Assembly to Front Body within Tunnel

    Lowering of TBM Cutter Head towards TBM on Cradle

    Connecting TBM Middle Body onto TBM Front Body on Cradle

    PIE – Assembly of Herrenknecht TBM MAIN DRIVE


    Gantry 1 Hoisted Up for Conversion

    Grantry 7 hoisted and to be lowered into Tunnel Shaft

    Probe Drill Bridge installed with customized Support Structures

    Probe Drill Bridge installed with Rollers for rail mount maneuvering in Tunnel

    PIE – Assembly of Herrenknecht TBM


    Front Body to be hoisted and lowered into Tunnel

    Cutter Head to be lowered and assembled within Tunnel

    Tail Skin lowered and to be attached to Middle Body Assembly

    Installation of TBM accessories such as Slurry Pipes, Control Valves and Working Platform etc.

    BENOI JURONG ISLAND – Assembly of Kawasaki TBM


    TBM Front Body assembled with Cutter Motor and Man Lock to be hoisted into Tunnel

    Installation of Slurry Pipes and Accessories

    Installation of Electrical Ball Valves onto Middle Body Shield Jack Area

    Removal f Lifting Lugs when Cutter Head is in position